Construction and Renovation Plans at Hanshin Port Container Terminals(Fiscal 2014~2016)

航路

Port Island Container terminals (PC-15~17)

Fiscal 2016 Wharf renovated to be earthquake-resistant and 16m-deep
Fiscal 2013 and 2014  5 gantry cranes renovated to 22 ranks at PC-16/17
Fiscal 2016~  2 gantry cranes planned to be renovated to 22 ranks at PC-15

Sakishima Container City terminals (C-8)

Fiscal 2016~2018 2 gantry cranes to be replaced to 17 ranks

Rokko Island Container terminals (RC-6〜7)

Fiscal 2013 ~ Wharf being renovated to be earthquake-resistant and 16m-deep
Fiscal 2015 3 gantry cranes to be renovated to 22 ranks
Fiscal 2015~2017 2 gantry cranes to be renovated to 22 ranks

Sakishima Container terminals (C-9)

Fiscal 2015 2 gantry cranes to be replaced to 17 ranks
Fiscal 2015~2016
 Transfer cranes to be introduced

Sakishima Container terminals (C-4)

Fiscal 2015 1 gantry crane replaced to 17 ranks
Fiscal 2016 1 gantry crane replaced to 17 ranks

Sakishima Container terminals (C-12)

Fiscal 2013 ~ Wharf being extended and constructed to be earthquake-resistant and 16m-deep